Sidewalk Maintenance Program
The City of Gahanna places a high priority on maintenance of the City's infrastructure, including maintaining a safe sidewalk network throughout the City. Sidewalks that are in good repair promote community-wide safety and enhance connectivity and walkability.
Sidewalk Maintenance (4.16 Miles) | Grind | Replace |
| Beaverbrook Ct (Beaverbrook Dr to End of Ct) | June 30 | July 9 |
| Caro Pl (Caroway Blvd to End of Ct) | July 2 | July 9 |
| Caswell Dr (Buttonwood Ct to Schillingwood Dr) | Aug 4 | Aug 4 |
| Chilton Pl (Skinner Ave to End of Ct) | Sept 11 | Sept 1 |
| Dellfield Ln (Caroway Blvd to End of Ct) | July 7 | July 14 |
| Harmony Ct (Helmbright Dr to End of Ct) | Aug 4 | Aug 11 |
| Harmony Dr (Helmbright Dr to Shady Spring Dr) | Aug 4 | Aug 11 |
| Havelock Ct (Beaverbrook Dr to End of Ct) | June 30 | July 9 |
| Helmbright Dr (Leaflock Ct to Tamara Dr N) | July 10 | July 28 |
| Hunters Glen Dr (Helmbright Dr to Beaverbrook Dr) | Aug 4 | Aug 4 |
| Newton Ct (Emory St to End of Ct) | Aug 1 | Sept 1 |
| Rocky Fork Ct (Rocky Fork Blvd to End of Ct) | July 2 | July 18 |
| Schillingwood Dr (Helmbright Dr to Caswell Dr) | July 16 | July 24 |
| Shady Springs Dr (Beaverbrook Dr to Harmony Dr) | Aug 4 | Aug 11 |
| Tabon Ct (Dellfield Way to End of Ct) | July 8 | July 18 |
| Tamara Dr S (Tamara Dr N to Helmbright Dr) | July 9 | July 18 |
| Westerdale Dr (Schillingwood Dr to Oakshade Dr) | Aug 18 | Aug 25 |
Sidewalk Maintenance Program Schedule:
All schedule changes will be updated on this website page. The program schedule is subject to change. Please check back for more information.
Resources
Sidewalk Maintenance | GRIND | REPLACE |
| BEAVERBROOK DR (BARDEN CT TO HUNTERS RUN W) | ||
| BEAVERBROOK DR (BARDEN CT TO HELMBRIGHT DR) | ||
| BARDEN CT | ||
| CHALLIS SPRINGS DR (HARRISON Pond Dr to CLARK STATE) | ||
| AROYA CT | ||
| CHERRYSTONE DR N & S (TRAPP DR TO TRAPP DR) | ||
| TRAPP DR (CHERRYSTONE DR N TO CROSSING CREEK N) | ||
| LANG DR (RIVA RIDGE BLVD TO END) | ||
| LANG DR (BRYN MAWR DR TO END) | ||
| MISTLE TOE ST (MOSS OAK AVE TO THISTLE AVE) | ||
| SANDBURR (STYGLER TO WINDBOURNE) | ||
| SPIREA AVE ( MISTLETOE TO END) |
Sidewalk Maintenance Program Schedule:
All schedule changes will be updated on this website page. The program schedule is subject to change.
May 2023: Sidewalk Inspection
September 2023: Notice Served to Property Owner
November 3, 2023: Appeal Request Deadline to Property Appeals Board
November 22, 2023: Deadline to Opt Out of Program
May 22, 2024: Construction by Property Owner Deadline (or as consistent with approved right-of-way permit)
Summer 2024: Construction by City Begins
Fall 2024: Construction by City Complete
Fall 2024: Assessment Notice Served to Property Owner
2025: Assessment Effective
Resources
Sidewalk Maintenance
| Grinding | Replacement | |
| Ashford Glen Ct | 5/9/2024 | 5/24/2024 |
| Ashford Glen Dr | 5/9/2024 | 6/3/2024 |
| Avonwick Pl | 5/6/2024 | 5/20/2024 |
| Haymarket Pl | 5/1/2024 | 5/14/2024 |
| Codet Rd | 4/16/2024 | 5/6/2024 |
| Lincolnshire Rd | 4/16/2024 | 5/6/2024 |
| Riva Ridge Blvd | 5/13/2024 | 6/6/2024 |
Sidewalk Maintenance Program Schedule:
All schedule changes will be updated on this website page. The program schedule is subject to change.
- Fall 2022: Sidewalk Inspection
- March 10, 2023: Notice Served to Property Owner
- April 2023: Initial Notice Rescinded
- September 2023: Notice Reissued to Property Owner
- October 27, 2023: Appeal Request Deadline to Property Appeals Board
- November 22, 2023: Opt Out Deadline
- May 22, 2024 or as consistent with approved ROW permit: Construction by Property Owner Deadline
- Spring 2024: Construction by City Begins
- Summer 2024: Construction by City Complete
- Fall 2024: Assessment Notice Served to Property Owner
- 2025: Assessment Effective
Resources
- Sidewalk Maintenance Guidelines
- Right-of-Way Construction Permit Application
- 2022 Sidewalk Program Map
Sidewalk Maintenance Program Schedule
All schedule changes will be updated on this website page. The program schedule is subject to change.
For more information about the schedule and how we got to where we are today, view the recording of the May 9, 2022 Council Committee meeting on our YouTube channel. (Presentation begins at 56:09)
- Winter 2021 through Spring 2022: Sidewalk Inspection
- July 1, 2022: Notice Served to Property Owner
- July 15, 2022: Remarking Request Due
- July 31, 2022: Appeal Request Deadline to Property Appeals Board
- August 15, 2022: Property Owner Opt-Out Deadline
- October 14, 2022: Construction by Property Owner Deadline
- March 2023: Construction by City Begins
- Summer 2023: Construction by City Complete
- Fall 2023: Assessment Notice Served to Property Owner
- 2024: Assessment Effective
Resources
-
Sidewalk Maintenance